- ENGINEER COMPETENCY
Pressure systems are everywhere — from compressed-air ring mains to steam boilers, autoclaves and process vessels. PSSR 2000 puts the responsibility for safe operation squarely on the duty-holder, and that responsibility is most often discharged by the plant manager. This checklist sets out what you should have in place before, during and after a PSSR examination — and the common findings that trip sites up.
PSSR applies to systems containing a “relevant fluid” — steam, compressed or liquefied gas above 0.5 bar, and pressurised hot water above 110°C. Boilers, receivers, accumulators, vessels and the protective devices that serve them all fall in scope. Domestic systems are excluded; almost every industrial site has something in scope.
You cannot lawfully operate most pressure systems without a Written Scheme of Examination drawn up by a competent person. The scheme lists every item to be examined, the frequency, and the protective devices to be tested. It is a living document — when you add, modify or decommission equipment, the scheme must be updated by a competent person before the change goes live.
Before the engineer arrives, work through the following:
Expect the engineer to work through the system end-to-end:
Recurring issues we see across UK sites include corrosion on the underside of receivers where condensate gathers, safety valves seized through lack of regular lifting, documentation gaps where modifications never made it into the scheme, and missing or illegible nameplates. Most are avoidable with a simple monthly walk-round and a clear change-control process.
Reports of Examination must be kept until at least the next examination — for the life of the equipment in practice. Treat them as a legal record, not paperwork. The HSE will ask to see them, and insurers will too at renewal.
PSSR competence is sector-specific. The engineer who knows your steam plant is rarely the same one who examines your autoclaves. ESiNet matches you with inspection engineers whose discipline aligns with your equipment and your sector.
Some insurers offer engineering inspection services through subsidiary companies, and those can act as the competent person. The key test is independence and qualification, not the parent organisation.
It depends entirely on the system. A single air receiver might take an hour. A steam plant with multiple boilers, pipework and safety devices can run across several days. The Written Scheme should give you a realistic timing per item.
Most pressure vessel examinations require depressurisation and isolation, which usually means stopping the system or that part of the system. Some external examinations and protective device checks can be done during operation. Plan around scheduled shutdowns where possible.
The engineer records it on the Report of Examination with a timescale for action. Immediate defects mean the system is out of service until repaired. Deferred actions need a documented close-out plan within the timescale set.
Request an inspection, or get in touch to discuss a Written Scheme of Examination.